WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

292

Discipline/Origin

Drilling
No origin

Well

Brasse
31/7-3 A

Date created

2019/10/03
2256 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Transocean Arctic


What happened in Reservoir section:
Stuck with wireline toolstring 1A ZAIT-PEX-PPC-MSIP-PPC-NGI-XPT at 2831 m, bottom of toolstring and top of toolstring 2779 m. Pulled tension on winch up to 14000 lbf and helf for 2 hours. No tension seen on cable head, indicatinf cable stuck. Not able to pull toolstring free.

What Was Planned

Wireline

What Was Learned

The cable head was checked on surface after toolstring ! A was fished and pulled to surface. With 1.5 m cable left on cable head everything was fine electrically.

What Actions Are Required

Suggest to split run 1A into two runs and perform pressure points on seperate WL run.